Demolition work at the Mongkok HSBC headquarters

Methods: Remote robots Brokk 40,50 and hydraulic crusher

Project highlight: Demolishment of canopy

The original appearance of the demolished canopy.

Because of tight construction schedule, 2 r emote robots Brokk 40,50 are applied at the same time.

Low noise and environmental–friendly robots for demolishment are necessary as the construction is carried out in downtown.